What is the earned value term for "What do we now think the total project will cost."?
CPI
ETC
EAC
The customer has lost confidence in the contractor and terminated the project early. What is this called?
Mutual Agreement
Termination for Default
Termination for Convenience of Buyer
You are managing a project. The project has a budget of $1500 and is 40% complete. The project has a 3-month project and you planned to spend $500 per month (have $500 worth of work completed each month). What is the value for SPI _________ at the end of the first month?

Answers

Answer 1

The earned value term for "What do we now think the total project will cost" is EAC. The Customer's loss of confidence in the contractor and ending the project early is known as Termination for Default.  the value for SPI at the end of the first month is:SPI = EV / PV = $200 / $166.67 = 1.2 ≈ 0.8 (rounded to one decimal place

The value for SPI at the end of the first month would be 0.8. Given the following details: Project budget: $1500Project duration: 3 months. Planned budget per month: $500Work completed: 40%SPI (Schedule Performance Index) is a metric that compares the project's performance to the planned schedule. This metric determines whether a project is ahead of schedule or behind schedule.The SPI formula is given by:SPI = EV / PVWhere EV is the earned value and PV is the planned value.

Using the formula for the SPI, we can determine the SPI value at the end of the first month as follows:PV = 1 * $500 = $500EV = 40% * $1500 = $600SPI = EV / PV = $600 / $500 = 1.2the planned value (PV) for the first month would be $500 * 1/3 = $166.67.The earned value (EV) at the end of the first month would be 40% * $1500 * 1/3 = $200.

Learn more about value term here:https://brainly.com/question/11546044

#SPJ11


Related Questions

1 Profit Max with MC & MR: 2. Different Degrees of Price Discrimination: 3. Nash Equilibrium vs. Dominant Strategy: 4. How are MC markets like PC markets and how are they like monopolies?

Answers

Profit maximization occurs where marginal revenue equals marginal cost.

The profit maximization principle applies to all firms, whether they are monopolies or competitive, and it provides a standard to help firms determine their optimal output level and price. To maximize profits, firms must find the point where marginal revenue (MR) equals marginal cost (MC). Different degrees of price discrimination exists, and firms can engage in this practice by charging different prices to different customers for the same good or service. First-degree price discrimination, second-degree price discrimination, and third-degree price discrimination are the three types of price discrimination. Each form has a different impact on consumer welfare and market efficiency.

Nash equilibrium and dominant strategy equilibrium are two concepts that help us understand strategic interactions between decision-makers. When a player's optimal strategy is independent of the choices of other players, a dominant strategy equilibrium occurs. When no player can increase their payoff by deviating from their current strategy given the other players' strategies, a Nash equilibrium occurs. Marginal cost (MC) markets are like perfect competition markets because there are numerous sellers and buyers, which implies that no one has the power to influence the market price. MC markets are similar to monopolies in that they are capable of earning economic profits in the short run.

To know more about the  profit maximization visit:

https://brainly.com/question/29989740

#SPJ11

During 2020, Harmony Co. sold $528,000 of merchandise at marked retail prices. At the end of 2020, the following information was available from its records: At Cost At Retail Beginning inventory Net purchases $135,600 239, 240 $264,800 401,600 Assume that in addition to estimating its ending inventory by the retail method, Harmony Co. also took a physical inventory at the marked selling prices of the inventory Items at the end of 2020. Assume further that the total of this physical Inventory at marked selling prices was $110,000. a. Determine the amount of this inventory at cost. (Round your Intermediate calculations and final answer to 2 decimal places.) Inventory at cost b. Determine Harmony's 2020 Inventory shrinkage from breakage, theft, or other causes at retail and at cost. (Round your Intermediate calculations and final answers to 2 decimal places.) At Cost At Retail Estimated inventory that should have been on hand Physical inventory Inventory shrinkage

Answers

Based on the given information, the inventory at cost at the end of 2020 for Harmony Co. can be determined to be $219,720. Additionally, the inventory shrinkage for 2020, both at retail and at cost, can be calculated.

To calculate the inventory at cost at the end of 2020, we need to use the retail method. The retail method calculates the cost of inventory by applying a cost-to-retail ratio to the retail value. The cost-to-retail ratio is determined by dividing the cost of goods available for sale by the retail value of goods available for sale.

Cost-to-retail ratio = Cost of goods available for sale / Retail value of goods available for sale

Cost of goods available for sale = Beginning inventory + Net purchases

Retail value of goods available for sale = Beginning inventory at retail + Net purchases at retail

Using the given values:

Cost of goods available for sale = $135,600 + $239,240 = $374,840

Retail value of goods available for sale = $264,800 + $401,600 = $666,400

Cost-to-retail ratio = $374,840 / $666,400 ≈ 0.5624

To determine the inventory at cost, we multiply the physical inventory at retail ($110,000) by the cost-to-retail ratio:

Inventory at cost = Physical inventory at retail * Cost-to-retail ratio

Inventory at cost = $110,000 * 0.5624 = $61,864

Therefore, the inventory at cost at the end of 2020 for Harmony Co. is approximately $61,864.

Regarding the inventory shrinkage, it can be calculated by comparing the estimated inventory that should have been on hand with the physical inventory.

Estimated inventory that should have been on hand = Beginning inventory + Net purchases - Inventory shrinkage

Inventory shrinkage = Beginning inventory + Net purchases - Estimated inventory that should have been on hand

Using the given values:

Estimated inventory that should have been on hand = $135,600 + $239,240 - $110,000 = $264,840

Inventory shrinkage = $135,600 + $239,240 - $264,840 = $110,000

Learn more about inventory here:

https://brainly.com/question/29944146

#SPJ11

an increase in federal income tax rates is an example of fiscal
policy that affects GDP indirectly True or False?

Answers

True. An increase in federal income tax rates is an example of fiscal policy that affects GDP indirectly.

Fiscal policy refers to the use of government spending and taxation to influence the economy. When federal income tax rates are increased, it affects individuals and businesses' disposable income, reducing the amount of money available for consumption and investment. As a result, this can indirectly impact GDP (Gross Domestic Product) by influencing consumer spending and business investment. When tax rates increase, individuals and businesses may reduce their spending and investment activities, leading to a decrease in aggregate demand. Lower aggregate demand can result in decreased production, reduced employment, and potentially lower economic growth, thus affecting GDP indirectly. Therefore, an increase in federal income tax rates is considered a fiscal policy tool that has an indirect impact on GDP.

Learn more about fiscal policy here:

https://brainly.com/question/1114207

#SPJ11

1. What is the scope of the operations? 2. Based on our reading, what roles/functions most likely exist
within this operation and how do they interface with each
other? 3. Is this a product or ser
In 2019, the Ryan Company was struggling in their manufacturing plant with the assembly of its most recent tool supporting all the local auto manufacturers. The Operations Manager had been reviewing t

Answers

The scope of the operations in the scenario you provided is the manufacturing plant of the Ryan Company, specifically focused on the assembly of a tool supporting local auto manufacturers.

Based on the information provided, the roles/functions that most likely exist within this operation include:

Operations Manager: Responsible for overseeing the overall operations of the manufacturing plant, including the assembly process. They would be involved in reviewing the performance and identifying areas of improvement.Production Supervisor: In charge of supervising the assembly line and ensuring that the production targets are met. They would manage the day-to-day operations, coordinate with the workers, and address any issues that arise.Assembly Workers: These individuals are responsible for physically assembling the tool. They follow the instructions, use the necessary tools and equipment, and work together to complete the assembly process.Quality Control Inspector: Ensures that the assembled tool meets the required quality standards. They perform inspections, tests, and checks at different stages of the assembly process to identify any defects or issues.

Learn more about  tool supporting here

https://brainly.com/question/16579489

#SPJ11

In the CAR® RPA, mediation is
a. Required only if other forms of dispute resolution fail.
b. Required whether the parties agree to any other form of dispute
resolution of not.
c. Required to resolve disputes between the seller and the seller’s
broker, but not required to resolve disputes between the seller and
the buyer.
d. Recommended, but never required.

Answers

Mediation in the CAR® (California Association of Realtors®) RPA (Residential Purchase Agreement) is required whether the parties agree to any other form of dispute resolution or not. This means that regardless of any alternative methods the parties may prefer, mediation is a mandatory step in the resolution process.

Mediation serves as a crucial and obligatory step in the CAR® RPA for addressing disputes between the parties involved in a real estate transaction. It is not solely dependent on other forms of dispute resolution failing, but rather it is required from the outset.

Mediation provides an opportunity for the parties to resolve their conflicts through a facilitated negotiation process with the assistance of a neutral mediator. It aims to foster open communication, understanding, and mutual agreement, promoting a more amicable and efficient resolution. The requirement for mediation emphasizes the importance of exploring non-adversarial methods to resolve disputes and encourages parties to work towards a mutually acceptable outcome.

To learn more about CAR: -brainly.com/question/31448756

#SPJ11

7.For a particular time study a company would like to be 90%
confident that the average job cycle time is within 5% of the true
average job cycle time. Assume that the average job cycle time was
15.76

Answers

To be 90% confident that the average job cycle time is within 5% of the true average job cycle time, a company can use statistical methods to determine the required sample size. Assuming the average job cycle time is 15.76, the company needs to calculate the sample size to achieve the desired level of confidence.

To calculate the required sample size, the company can use the formula for sample size determination based on confidence level and margin of error. In this case, the desired confidence level is 90% (which corresponds to a z-score of 1.645 for a two-tailed test) and the desired margin of error is 5% of the average job cycle time.

Using the formula:

Sample Size = (Z-score)^2 * (Standard Deviation)^2 / (Margin of Error)^2

Since the standard deviation is not given in the question, it is not possible to calculate the exact sample size. The company would need to have historical data or estimates of the standard deviation to determine the required sample size accurately. However, if the company has an estimate of the standard deviation or can make an assumption, they can plug in the values into the formula to calculate the sample size needed to achieve the desired confidence level and margin of error. This sample size will ensure that the company is 90% confident that the average job cycle time is within 5% of the true average job cycle time.

Learn more about error here: https://brainly.com/question/30759250

#SPJ11

Question 2 > Last quarter's revenue would be considered: A lagging indicator. O A leading indicator. O An economic indicator. O A future indicator.

Answers

Last quarter's revenue is considered a lagging indicator because it reflects past performance rather than providing information about future trends or acting as a leading indicator.

A lagging indicator is a metric or factor that follows or lags behind changes in the overall economic or business environment. It reflects past performance and is typically used to confirm trends or analyze the impact of previous events. In the context of financial analysis, revenue is often considered a lagging indicator because it represents the income generated from past sales or business activities.

By looking at last quarter's revenue, businesses and analysts can assess the financial results and performance of a company during a specific period that has already occurred. It provides insights into how well the company has performed in terms of generating sales and generating revenue in the past. However, it does not provide information about future trends or predict upcoming changes in the business environment.

In contrast, leading indicators are metrics or factors that provide insights into potential future trends or changes. They are used to forecast or predict future performance and help businesses make proactive decisions. Examples of leading indicators could include new orders, customer inquiries, or economic indicators such as consumer confidence or housing starts.

Therefore, last quarter's revenue is considered a lagging indicator because it reflects past performance rather than providing information about future trends or acting as a leading indicator.

Learn more about indicator here

https://brainly.com/question/29839345

#SPJ11

IV II LII Base Base Ba se Base Base Tax income) Tax (income) Tax (income) Tax (income) Tax (income) $30 S 100 $10 $100 $ 5 $100 $ 30 $100 S 10 $100 50 200 20 200 15 200 60 200 30 200 60 300 30 300 30 300 90 300 60 300 70 400 40 400 50 400 120 400 100 400 Which of the above schedules represent(s) a progressive tax? OO A. B. V only III and V C. III only D. II and III

Answers

A progressive tax is a tax that imposes a greater burden on the wealthy than on the poor. The taxpayers pay the same rate regardless of income, so there is no difference in tax burden between the rich and the poor. The correct answer is Option D.

This is the opposite of a regressive tax, which imposes a greater burden on the poor than on the wealthy.  A proportional tax is a tax that imposes an equal burden on all taxpayers, regardless of their income level. Schedules II and III represent progressive tax rates. As income increases, the percentage of income paid in taxes increases. The higher the income, the greater the tax burden, and the lower the income, the lower the tax burden. As a result, this system is progressive. There are fixed tax rates in schedule I, but the amount of money taxed varies depending on the taxpayer's income. Schedules IV and V are proportional taxes, as they have a fixed tax rate and the same percentage of income is taxed for all taxpayers, regardless of income level. The taxpayers pay the same rate regardless of income, so there is no difference in tax burden between the rich and the poor. The correct answer is Option D.

learn more about income

https://brainly.com/question/14732695

#SPJ11

The Income statement for a corporation shows a Gross Profit of $120,000, Net Sales of $560,000 and Operating expenses of $50,000. Which of the follow is true? a. Net Income is $70,000. b. Net income is $390,000. c. Cost of Goods sold is $70,000. d. Cost of Goods Sold is $490,000

Answers

a. Net Income is $70,000. Net income can be calculated by subtracting operating expenses from the gross profit. In this case, Net Income = Gross Profit - Operating expenses = $120,000 - $50,000 = $70,000. Therefore, option a is true.

to determine the net income of the corporation. The gross profit is stated as $120,000, which represents the total revenue minus the cost of goods sold. The net sales are given as $560,000, indicating the total revenue generated from sales. The operating expenses are mentioned as $50,000, representing the costs incurred in running the business. To calculate the net income, we subtract the operating expenses from the gross profit. Therefore, Net Income = Gross Profit - Operating expenses = $120,000 - $50,000 = $70,000. This means that after accounting for all expenses, the corporation's net income is $70,000.

learn more about gross profit here:

https://brainly.com/question/29064762

#SPJ11

As shown in the appendix to chapter 4, the Cobb-Douglas form of utility function, U(X,Y) = a log(X) + (1-a) log(Y), yields demand functions X = (a/Px)I and Y = [(1-a)/Py]l. These demand functions have some unique properties. One is that the cross-price elasticities are zero, as pointed out in the appendix, because neither demand depends on the price of the other good. Another unique property is that the own-price elasticities are constant and do not depend on the particular values of the prices and income. Using calculus, the price (Enter your response as real Px ax = elasticity of demand for good X can be calculated as Ep Therefore, the price elasticity of demand for good X equals X OP X number rounded to one decimal place.) The income elasticity of demand also does not depend on the values of prices and income. The income elasticity of demand for good X can be calculated as I ax (Enter your response as a real number rounded to one decimal place.) E₁ = The income elasticity of demand for good X is therefore X di One other unusual property of these demand functions is that the consumer spends a fixed proportion of income on each good regardless of the values of the prices and income. The fraction of income spent on good X is a 1/Px 1/2

Answers

To calculate the price elasticity of demand for good X using the Cobb-Douglas utility function, we need to differentiate the demand function for X with respect to its own price (Px).

These demand functions have some unique properties. One is that the cross-price elasticities are zero, as pointed out in the appendix, because neither demand depends on the price of the other good. Another unique property is that the own-price elasticities are constant and do not depend on the particular values of the prices and income. Using calculus, the price (Enter your response as real Px ax = elasticity of demand for good X can be calculated as Ep Therefore, the price elasticity of demand for good X equals X OP X number rounded to one decimal place.) The income elasticity of demand also does not depend on the values of prices and income. The income elasticity of demand for good X can be calculated as I ax (Enter your response as a real number rounded to one decimal place.) E₁ = The income elasticity of demand for good X is therefore X di One other unusual property of these demand functions is that the consumer spends a fixed proportion of income on each good regardless of the values of the prices and income.

learn more about price here

https://brainly.com/question/19091385

#SPJ11

Achart (mph) is a graph for proportions. True or False?

Answers

The statement "Achart (mph) is a graph for proportions" is False.

An Achart is not a graph for proportions, rather, it is a graphical representation of the acceleration of an object with respect to time. Achart is a type of motion graph that is often used to represent the movement of an object undergoing constant acceleration. It shows the change in velocity over time.

A proportion is a statement that two ratios are equal. For instance, in a statement like 2/4 = 4/8, the ratios on each side of the equal sign are equal, so the statement is a proportion. Proportions are widely used in mathematics and other disciplines, and they are used to solve a variety of problems.

You can learn more about Achart at: https://brainly.com/question/32416106

#SPJ11

You have $500,000 available to invest. The risk-free rate, as well as your borrowing rate, is 8%. The return on the risky portfolio is 16%. The standard deviation on the risky portfolio is 50%.
a. If you wish to earn a 22% return, how much money should you borrow?
b. If the standard deviation on the complete portfolio is 25%, what is the expected return on the complete portfolio?

Answers

a. If you want to earn a 22% return. we can use the formula for required return to calculate the maximum borrowing amount:$500,000 = X + ($500,000 - X)(22% - 8.25%) / (16% - 8.25%)$500,000 = X + $346,620.69 / 0.0775$500,000 = X + $4,471,158.06X = -$3,971,158.06 As a result, you shouldn't borrow any money. b. If the standard deviation on the complete portfolio is 25%. Therefore, the expected return on the complete portfolio is 19.25%.

a. If you want to earn a 22% return. To calculate the expected return on the portfolio, the following formula is used:R_p = R_f + β_p (R_m - R_f) Here,R_p = expected return on portfolio,R_f = risk-free rate = 8%,R_m = market return = 16%, andβ_p = beta of the portfolio. For this question, the beta of the portfolio is not given. Instead, the standard deviation is given. As a result, to compute beta, we must first utilize the following equation:Beta = Standard Deviation / Market Return Beta = 0.50 / 16 Beta = 0.03125After calculating beta, we can use it to calculate the expected return on the portfolio.R_p = 8% + 0.03125 (16% - 8%)R_p = 8% + 0.25R_p = 8.25%We can use the CAPM model to determine the minimum rate of return required to finance the project as follows:R_i = R_f + β_i (R_m - R_f)R_i = 8% + β_i (16% - 8%)R_i = 8% + 0.03125 (16% - 8%)R_i = 8% + 0.25R_i = 8.25%Now we can use the formula for required return to calculate the maximum borrowing amount:$500,000 = X + ($500,000 - X)(22% - 8.25%) / (16% - 8.25%)$500,000 = X + $346,620.69 / 0.0775$500,000 = X + $4,471,158.06X = -$3,971,158.06 As a result, you shouldn't borrow any money.

b. If the standard deviation on the complete portfolio is 25%, We know that,R_p = expected return on the portfolio,R_f = risk-free rate = 8%,R_m = market return = 16%, andβ_p = beta of the portfolio.β_p = Standard Deviation / Market Return = 25% / 16% = 1.5625R_p = R_f + β_p (R_m - R_f) = 8% + 1.5625 (16% - 8%)= 19.25%Therefore, the expected return on the complete portfolio is 19.25%.

To know more about maximum borrowing visit:

https://brainly.com/question/30463552

#SPJ11

QUESTION 6 Two assets with a beta of one should have the same covariance with the market. O True O False

Answers

The correct option is "true". The beta is the ratio of a stock's covariance to the market's variance. Beta measures the degree to which a stock's price moves in conjunction with the market. Beta compares an asset's volatility to that of the market as a whole, using the S&P 500 index as the market benchmark. An asset with a beta of 1 is expected to move in tandem with the market as a whole. If the market has a positive return, a stock with a beta of 1 is expected to produce a positive return.

Alternatively, if the market has a negative return, the stock's return is expected to be negative as well. A stock with a beta of less than 1 is predicted to be less volatile than the market. Stocks with a beta of less than 1 are viewed as "safer" because they are less volatile.

However, if the market has a positive return, stocks with a beta of less than 1 will have a lower positive return than the market as a whole. Conversely, when the market has a negative return, the stock will have a lower negative return than the market as a whole.

In conclusion, two assets with a beta of one should have the same covariance with the market. The covariance is a statistical calculation that measures the degree to which two variables fluctuate together. The stock's price fluctuation is compared to the market index in a covariance calculation. As a result, stocks with a beta of 1 are more sensitive to market movements and are more volatile than those with a beta of less than 1.

To know more about benchmarks, visit:

https://brainly.com/question/1104065

#SPJ11

​(Future value​) Selma and Patty Bouvier are​ twins, and both work at the Springfield DMV. They decide to save for​ retirement, which is 35 years away. They'll both receive an annual return of 8% on their investment over the next 35 years. Selma invests $1500 per year at the end of each year only for the first 10 years of the 35 year period for a total of $15000 saved. Patty​ doesn't start saving for 10 years and then saves $1,500 per year at the end of each year for the remaining 25 years for a total of $37,500 saved. How much will each of them have when they​ retire?

Answers

Selma and Patty Bouvier are twins who work at the Springfield DMV and are saving for retirement, which is 35 years away.

Selma invests $1,500 per year for the first 10 years, while Patty starts saving after 10 years and also invests $1,500 per year for the remaining 25 years. They both receive an annual return of 8% on their investments. We need to calculate how much they will have when they retire.

Selma invests $1,500 per year for the first 10 years, so the future value of her investment can be calculated using the formula for the future value of an ordinary annuity:

FV = PMT * ((1 + r)^n - 1) / r

where FV is the future value, PMT is the annual payment, r is the annual interest rate, and n is the number of years.

Substituting the given values, we get:

FV(Selma) = 1500 * ((1 + 0.08)^10 - 1) / 0.08

≈ $27,512.07

Selma will have approximately $27,512.07 when she retires.

Patty starts saving after 10 years and invests $1,500 per year for the remaining 25 years. We can calculate her future value using the same formula:

FV(Patty) = 1500 * ((1 + 0.08)^25 - 1) / 0.08

≈ $118,792.47

Patty will have approximately $118,792.47 when she retires.

Therefore, Selma will have around $27,512.07, and Patty will have around $118,792.47 when they retire.

Learn more about investment from here:

https://brainly.com/question/30105963

#SPJ11

How do organizations learn and remember? Why do they
forget?
(Support with references)

Answers

Organizations learn and remember through a combination of individual, group, and organizational memory processes. Individual memory involves the storage and retrieval of information by individual employees. Group memory refers to the storage and retrieval of information within groups, such as departments or teams.

Organizational memory encompasses all of the processes that allow an organization to store and retrieve information, including databases, policies and procedures, and the institutional knowledge of employees.Organizations forget because of a variety of reasons, including the loss of key personnel, changes in leadership or strategy, and the lack of formal mechanisms for storing and retrieving information. When key employees leave an organization, they take with them their individual and group memories, which can be difficult to replace. Changes in leadership or strategy can also lead to the loss of institutional memory, as new leaders may not be aware of past practices or may not value them

The lack of formal mechanisms for storing and retrieving information can also contribute to forgetting. Without a centralized database or other formal system for storing information, organizations may rely on individual memories or informal group memories to store and retrieve information. This can lead to important information being lost when key employees leave or when informal groups disband.

To know more about Organizations visit:

brainly.com/question/28272058

#SPJ11

If low and stable inflation is beneficial, why does
the Central Bank target a positive rate?

Answers

The Central Bank targets a positive rate of inflation because a low and stable inflation rate is considered beneficial for the economy.

A positive rate of inflation is targeted by the Central Bank for several reasons. First, a moderate level of inflation is believed to promote economic growth. It encourages spending and investment by reducing the incentive to hoard money. When people expect prices to rise gradually, they are more likely to spend and invest, stimulating economic activity.

Second, a positive inflation rate allows the Central Bank to have more flexibility in monetary policy. By maintaining a target inflation rate, the Central Bank can use interest rates and other tools to manage the economy effectively. It provides room for the Central Bank to stimulate or cool down the economy as needed.

Moreover, a positive inflation rate also helps to prevent deflation, which is generally considered more detrimental to the economy. Deflation, or a sustained decrease in the general price level, can lead to reduced consumption, delayed investments, and economic stagnation.

Overall, a positive inflation rate within a low and stable range allows the Central Bank to promote economic growth, maintain price stability, and have greater control over monetary policy.

Learn more about rate of inflation    

https://brainly.com/question/19263433

#SPJ11

in the semisubsistence economy that existed in the american backcountry, money was seldom seen and was used primarily to

Answers

In the semisubsistence economy that existed in the American backcountry, money was seldom seen and was used primarily to purchase luxury items and manufactured goods from other parts of the world.

A semisubsistence economy is one in which the production of goods is primarily for the purpose of personal consumption rather than for sale or trade. As a result, there is little surplus production available for trade or sale. Money was seldom seen in such economies, and when it was seen, it was primarily used to purchase luxury items and manufactured goods from other parts of the world.

The American backcountry was a region of the United States that was sparsely populated and located west of the Atlantic seaboard during the colonial era. This region was characterized by a semisubsistence economy, which was based on small-scale agriculture, hunting, and fishing, as well as the production of goods for personal consumption rather than for sale or trade.

Money was seldom seen in this economy, and when it was seen, it was primarily used to purchase luxury items and manufactured goods from other parts of the world.

To know more about backcountry visit:

https://brainly.com/question/14676950

#SPJ11

CH 5 KB In variable costing, which of the following will be included as part of inventory on a company's balance sheet? A. None of the answer choices will be part of inventory in variable costing. B. Variable selling cost C. Fixed selling costs D. Fixed production cost CH 5 KB.

Answers

In variable costing, Fixed production costs will be included as part of the inventory on a company's balance sheet.

In variable costing, Fixed production costs will be included as part of the inventory on a company's balance sheet.

Variable costing is also called direct costing, which is the cost of producing goods that varies depending on the number of products produced.

A company will only incur expenses when goods are sold.

The Fixed Production cost is part of inventory, in variable costing. Variable costing includes the direct costs of production and the variable overheads related to the production of goods.

Since direct labor and direct materials are the only costs that vary with the number of units produced, the variable costing approach only considers those costs as product costs and fixed overheads as period costs.

Fixed selling costs and variable selling costs are excluded from inventory and are expensed as incurred under variable costing because they are associated with the sales function of a business, rather than with production.

As a result, these costs are not included in inventory but are expensed in the period in which they are incurred.

Therefore, in variable costing, Fixed production costs will be included as part of the inventory on a company's balance sheet.

Know more about variable costing here:

https://brainly.com/question/31811001

#SPJ11

Problem 3-24 (Algo) Timely Transport provides local delivery service for a number f downtown and suburban businesses. Delivery charges are based on distance and weight involved for each delivery: 25 c

Answers

It ends with "25 c" and does not provide complete information about the delivery charges based on distance and weight. Please provide the complete question for me to be able to assist you better.

I need complete information and context to provide an accurate answer to your question. Without the complete question, I cannot provide a meaningful response. Please provide the complete question, and I'll be happy to assist you.

I understand you have a question related to Timely Transport and their delivery charges. However, the information provided is incomplete. Please provide the complete details of the problem, including the distance, weight, and the given formula to calculate the delivery charges. Once you provide the necessary information, I will be happy to provide you with an accurate .

To know more about delivery visit :

https://brainly.com/question/2500875

#SPJ11

CDB stock is currently priced at $54.72. The company will pay a dividend of 55. 42 next year and investors require a return of 10 53 percent onder stocks What is the dudand growth stock?

Answers

Assuming the dividend next year ($55.42) represents the expected dividend for the current year, the dividend discount growth rate is approximately 10.53%, and the estimated current year's dividend is approximately $49.94.

Stock Price = Dividend / (Required Rate of Return - Dividend Growth Rate)

Given:

Stock Price = $54.72

Dividend = $55.42

Required Rate of Return = 10.53%

Substituting the values into the DDM formula, we have:

$54.72 = $55.42 / (0.1053 - Dividend Growth Rate)

Simplifying the equation:

$54.72 * (0.1053 - Dividend Growth Rate) = $55.42

5.763216 - $54.72 * Dividend Growth Rate = $55.42

-$54.72 * Dividend Growth Rate = $55.42 - 5.763216

-$54.72 * Dividend Growth Rate = $49.656784

Dividend Growth Rate = $49.656784 / -$54.72

Dividend Growth Rate ≈ -0.9074

The dividend growth rate is approximately -0.9074 or -90.74%.

Note that a negative growth rate implies a decrease in dividends over time, which may not be a realistic scenario. It's important to double-check the provided data to ensure its accuracy, as a negative growth rate is unusual for a dividend growth stock.

To know more about discount click the link below:

brainly.com/question/31603195

#SPJ11

why is economic growth key for countries who want to escape poverty

Answers

Economic growth is key for countries that want to escape poverty because it can create new job opportunities, increase wages, and improve living standards. When a country experiences economic growth, it generates more output and income, which can be reinvested in its own economy, leading to a virtuous cycle of growth.

Increased economic activity also leads to greater tax revenues for the government, which can be used to fund public services such as education, healthcare, and infrastructure development. These investments can further drive economic growth by increasing productivity and efficiency.

Additionally, economic growth can attract foreign investment and trade, which can lead to increased employment opportunities and higher levels of economic activity. Foreign trade can bring in new technologies, skills, and ideas, creating opportunities for innovation and diversification of the economy.

Overall, sustained economic growth over a period of time provides a pathway for countries to raise their citizens' incomes and improve their standard of living. This process can help reduce poverty, inequality, and unemployment, laying the groundwork for long-term prosperity and development.

Learn more about Economic growth is key for countries from

https://brainly.com/question/30280812

#SPJ11

Currently, you can exchange $1 for either ¥106.16 or €.7574 in New York. In Tokyo, the exchange rate is ¥/€.0078. If you have $1,350, how much profit can you earn with triangle arbitrage?
Multiple Choice
$116.24
$157.40
$139.92
$132.55
$125.92

Answers

By engaging in triangle arbitrage, you can earn a profit of $139.92.

Triangle arbitrage involves taking advantage of exchange rate discrepancies between three currencies to make a risk-free profit. In this scenario, we will consider the exchange rates between USD (U.S. dollars), JPY (Japanese yen), and EUR (euro).

Given the exchange rates in New York, we can calculate the implied exchange rate between JPY and EUR:

JPY/EUR = JPY/USD * USD/EUR

JPY/EUR = 106.16 * (1/0.7574) = 140.14

Comparing the implied exchange rate of JPY/EUR (140.14) with the actual exchange rate in Tokyo (0.0078), we can see an opportunity for arbitrage.

To perform triangle arbitrage, we start with $1,350 and go through the following steps:

Convert $1,350 to JPY: $1,350 * 106.16 = ¥143,484

Convert JPY to EUR: ¥143,484 * 0.0078 = €1,119.51

Convert EUR back to USD: €1,119.51 * 0.7574 = $847.59

The final amount in USD after triangle arbitrage is $847.59. To calculate the profit, we subtract the initial amount of $1,350:

Profit = $847.59 - $1,350 = -$502.41

Since the profit is negative, it means that triangle arbitrage would result in a loss of $502.41. Therefore, none of the provided answer choices is correct.

To learn more about arbitrage click here:

brainly.com/question/30480233

#SPJ11

Provide and estimation of the cost of equity using the CAPM model re ? 4
Explain why the CAPM model may be incomplete to estimate the cost of capital?
Compute the WACC?
Given its equity beta of 0.8 and its debt beta of 0.2, what is the asset beta of the firm F?

Answers

Cost of equity using CAPM modelRe = Rf + Beta(Rm - Rf)where,Re is the cost of equity,Rf is the risk-free rate of return,Beta is the beta of the stock,Rm is the market return.Rf is given to be 3.5%Beta is given to be 0.8The market return is given to be 10%Rm - Rf = 10% - 3.5% = 6.5%Re = 3.5% + 0.8 × 6.5% = 8.3%.

The estimation of the cost of equity using the CAPM model Re is 8.3%.Explanation:The CAPM model may be incomplete to estimate the cost of capital for the following reasons:It assumes that the market portfolio can be fully represented by a single index. It assumes that the return on a security depends only on systematic risk. It assumes that beta can be determined precisely. These assumptions may not hold in reality.The CAPM model also has some limitations which include:It is based on unrealistic assumptions. It may not be applicable to all types of companies. It may not be effective in estimating the cost of equity for a particular company.Compute the WACCThe formula for the weighted average cost of capital (WACC) is as follows:WACC = (E/V) * Re + (D/V) * Rd * (1 - Tc)Where E is the market value of the company's equityD is the market value of the company's debtV = E + D is the total market value of the company's financingRe is the cost of equity is the cost of debtTc is the corporate tax rate.Equity = 7,500,000Debt = 2,500,000E + D = 7,500,000 + 2,500,000 = 10,000,000Re = 8.3%Rd = 6%Tax rate = 40%WACC = (7,500,000/10,000,000) * 8.3% + (2,500,000/10,000,000) * 6% * (1 - 40%)WACC = 7.1%Given its equity beta of 0.8 and its debt beta of 0.2, what is the asset beta of the firm F?Asset beta (BA) = (E/V) x Beta(E) + (D/V) x Beta(D) x (1 - Tc)BA = (7,500,000/10,000,000) x 0.8 + (2,500,000/10,000,000) x 0.2 x (1 - 0.4)BA = 0.56The asset beta of the firm F is 0.56.

To know more about CAPM  visit:

https://brainly.com/question/10593001

#SPJ11

In 2021, Borland Semiconductors entered into the transactions described below. In 2018, Borland had sued 15 mon shares $1 par common stock at $39 per share. Required: 733 Assuming that Borland retires shares it reacquires, record the appropriate journal entry for each of the following transactions of no entry is required for a transaction/event, select "No journal entry required in the first account field, Enter your answers in millions (i.e., 10,000,000 should be entered as 10)) 1. On January 2, 2021, Borland reacquired 12 million shares at $37.50 per share. 2. On March 3, 2021, Borland reacquired 12 million shares at $41 per share 3. On August 13, 2021, Borland sold 1 million shares at $47 per share. 4. On December 15, 2021, Borland sold 2 million shares at $41 per share. View transaction list Journal entry worksheet 2 3 4 Record the reacquisition of 12 million shares at $37.50 per share. Check my wark

Answers

The "Cost of treasury shares" in transactions 3 and 4 refers to the original cost at which the shares were reacquired by Borland.

I can assist you in providing guidance on the appropriate journal entries for the transactions you've described. Here are the journal entries for each transaction:

Reacquisition of 12 million shares at $37.50 per share:

Date: January 2, 2021

Debit: Treasury Stock (12,000,000 shares x $37.50)

Credit: Cash (12,000,000 shares x $37.50)

Reacquisition of 12 million shares at $41 per share:

Date: March 3, 2021

Debit: Treasury Stock (12,000,000 shares x $41)

Credit: Cash (12,000,000 shares x $41)

Sale of 1 million shares at $47 per share:

Date: August 13, 2021

Debit: Cash (1,000,000 shares x $47)

Credit: Treasury Stock (1,000,000 shares x Cost of treasury shares)

Sale of 2 million shares at $41 per share:

Date: December 15, 2021

Debit: Cash (2,000,000 shares x $41)

Credit: Treasury Stock (2,000,000 shares x Cost of treasury shares)

Please note that the "Cost of treasury shares" in transactions 3 and 4 refers to the original cost at which the shares were reacquired by Borland. Ensure that you substitute the appropriate values in the journal entries based on the given information.

It's essential to consult with your accounting principles or guidelines and double-check the accuracy of the figures before finalizing the journal entries.

Learn more about transactions here

https://brainly.com/question/28059483

#SPJ11

The Law affects the five business forces; what are the five
business forces and explain how each has an effect on a
business.

Answers

The five business forces are the following:1. Competitive rivalry2. Bargaining power of buyers3. Bargaining power of suppliers4. Threat of new entrants5.

Threat of substitutesThe Law affects the five business forces and how each has an effect on a business:1. Competitive rivalry- When there are a significant number of competitors, the competitive rivalry increases, which puts pressure on the business to provide better prices, quality and services to attract more customers.2. Bargaining power of buyers- This is the level of control that customers have over the company. If the business only has a few customers that purchase a lot of the company’s products, the bargaining power of buyers can increase because they can dictate prices, quality, and delivery times.3. Bargaining power of suppliers- This is the level of control that suppliers have over the company. If there are only a few suppliers and the company relies heavily on their products or services, the bargaining power of suppliers can increase.4. Threat of new entrants- This occurs when new businesses enter the market, which increases competition and can lower profits for existing businesses.5. Threat of substitutes- This occurs when there are alternative products or services available, which can be a threat to existing businesses if customers switch to the substitute product or service.Thus, it can be concluded that the Law affects the five business forces and how each has an effect on a business.

Learn more about Bargaining power here :-

https://brainly.com/question/28499756

#SPJ11

2.4 An automotive company uses a kanban system to support its transmission assembly. The following information is known about the component on the assembly: Annual usage = 45 000 (300 days per year) S

Answers

The kanban system contributes to the company's overall productivity and cost-effectiveness in managing their transmission assembly process.

An automotive company uses a kanban system for its transmission assembly, with an annual usage of 45,000 components over 300 working days. The kanban system is a lean manufacturing technique designed to manage work-in-progress inventory and production flow. By utilizing visual signals like cards or bins, it communicates to workers when to produce or restock components based on customer demand.

In this case, the company assembles transmissions, with a specific component being used at a rate of 45,000 units per year. The kanban system helps the company maintain an efficient production flow, avoiding excess inventory or stockouts.

To know more about transmission assembly visit:

brainly.com/question/29894240

#SPJ11

Autumn Designs & Decorators issued a 120-day, 5% note for $82,600, dated April 13 to Zebra Furniture Company on account.
Required:
a. Determine the due date of the note.
b. Determine the maturity value of the note. Assume a 360-day year when calculating interest. Do not round your intermediate calculations and round your final answer to the nearest dollar.
c. Journalize the entries to record the following: (1) receipt of the note by Zebra Furniture and (2) receipt of payment of the note at maturity. Refer to the chart of accounts for the exact wording of the account titles. CNOW journals do not use lines for journal explanations. Every line on a journal page is used for debit or credit entries. CNOW journals will automatically indent a credit entry when a credit amount is entered.

Answers

a. The note of 120 days was issued on April 13th. The due date of the note is August 11.  

b. Maturity value is calculated using the formula MV = P(1 + rt), which is $83,771.

The maturity value of the note can be determined by using the formula,

MV = P(1 + rt),

where P is the principal, r is the rate of interest, t is the time period in years and MV is the maturity value of the note. Given that the principal value is $82,600, the time period is 120 days and the rate of interest is 5%, the maturity value can be calculated as follows:

MV = $82,600(1 + (5/100) x (120/360)) = $83,771.

Therefore, the maturity value of the note is $83,771. The due date of the note is calculated by adding the time period of 120 days to the issuance date of the note which is April 13th. Therefore, the due date of the note is August 11.

To know more about the Maturity value visit:

https://brainly.com/question/24374294

#SPJ11

ASSIGNMENT ISSUES IN FINANCIAL ACCOUNTING
In this assessment you are to provide an accounting analysis
covering
the following aspects of an ASX company’s operations csl
compoany
1) An analysis of th

Answers

To perform an accounting analysis of CSL Limited, an ASX-listed company, it is essential to review their financial statements, including the balance sheet, income statement, and cash flow statement.

Analyze key areas such as liquidity, solvency, asset quality, revenue sources, profitability, expense analysis, operating cash flow, investing and financing activities. Assess the company's compliance with accounting standards and evaluate their revenue recognition and expense management practices. Additionally, examine how CSL Limited accounts for intangible assets. A comprehensive analysis requires access to the company's specific financial statements and disclosures to provide a more detailed assessment of their financial performance and accounting practices.

Learn more about financial accounting here : brainly.com/question/28189815
#SPJ11

running the cpu at a faster speed than the manufacturer recommends is called ________.

Answers

When the CPU is running at a faster speed than the manufacturer recommends, it is known as overclocking.

Overclocking refers to a technique for boosting a computer's performance by increasing the clock rate of the processor, allowing it to run at a higher frequency than the manufacturer recommends. Overclocking is a popular practice among gamers and hardware enthusiasts who want to get the most out of their system. They increase the clock rate of the processor, which, in turn, increases the CPU's performance.Overclocking your CPU can have several advantages, including improved performance, faster system responsiveness, and enhanced gaming capabilities. However, it is important to remember that there are also risks associated with overclocking. Overclocking can cause the CPU to generate more heat, which can lead to instability and reduced system reliability. Additionally, overclocking can void your CPU's warranty, which can lead to a voided warranty if it is not done properly. Therefore, it is critical to do your homework and understand the risks associated with overclocking before attempting to increase your CPU's clock rate.

To know more about manufacturer visit:

https://brainly.com/question/27814463

#SPJ11

Which of the following is correct?
Group of answer choices
Internal rate of return is the discount rate that yields a zero net present value.
If net present value of an investment is positive, its internal rate of return is below its coat of capital
If internal rate of return of an investment is high, the investment is acceptable.
If the cost of capital is higher than the internal rate of return, the investment is not acceptable.

Answers

Internal rate of return is the discount rate that yields a zero net present value.

The internal rate of return (IRR) is defined as the discount rate at which the net present value of an investment's cash flows equals zero. In other words, it is the rate at which the sum of the present values of future cash inflows equals the sum of the present values of future cash outflows. Therefore, the first statement is true.

The second statement is incorrect because if the net present value of an investment is positive, it means that the investment's internal rate of return is above its cost of capital, not below it.

The third statement is partially correct because a high internal rate of return indicates that the investment is potentially profitable. However, other factors such as risk and uncertainty also need to be considered before determining whether the investment is acceptable or not.

The fourth statement is correct because if the cost of capital is higher than the internal rate of return, it means that the investment is not generating enough returns to cover its cost of financing, and thus it is not acceptable.

Learn more about  Internal rate of return from

https://brainly.com/question/29581665

#SPJ11

Other Questions
Describe what function can be used to estimate probabilities and its reason. (Hint: For example, a linear equation is used for the linear regression.) which of the following reagents is best used in the conversion of methyl alcohol to methyl chloride? socl2 cl- nacl cl2/ch2cl2 HELP!!Here's a graph of a linear function. Write the equation that describes the function Meeting Up: Two old friends plan to meet at a conference in San Francisco, and they agree to meet by "the tower." After arriving in town, each realizes that there are two natural choices: Sutro Tower Coit. Not having cell phones, each must choose independently which tower to go to. Each player prefers meeting up not meeting up, and neither cares where this would happen. Model this as a normal form game and write down the matrix form of the game All of the Pythagorean identities are related. Describe how to manipulate the equations to get from sin? t + cos2 t = 1 to the form tan? t = sec? t - 1. (3 Pts.) if an object is placed 4.1 cm from a convex mirror with f = 4 cm, then its image will be enlarged and real. Explain what is the size effect. How should you construct a riskfactor (portfolio) to capture the size effect? A) Calculate the cost of the proposed building. Proposed building GFA 550 m2 = Cost/m2 = ? Index = 215 Analyzed building GFA = 450 m2 Cost/m2 OMR 1,500 H Index 200 H (5 m 8. The area of the parallelogram whose adjacent sides formed by the vectors usi+i-k and v= 2i-j+3k is a) 32 b) 12 c) 38 d) 38 2 e) None of the above. 9. The direction in which the function f(x,y) = x + xy + y increases most rapidly at the point P(-1, 1) is a) < > b) < 1/2, 2/2 > d) < = 1/2 - 1/2 > d) e) None of the above. aw Let w = + s, r = y + x cost and s= x + y sint. Then at -rxsin + sy cost r+5 rxsint-s y cost r+5 rxsint+s y cost r+ s sxsint-ry cos t d) r+ s e) None of the above. 10. a) b) c) is what percent of the mouses energy budget goes to basal metabolism? The marketing plan should includea. a competitor analysis.b. a summary of market assumptions.c. an analysis of alternative markets.d. a sales forecast broken down by government industrial classifications. Combinations of FunctionsQuestion 4 Let f(x) = (x 2) + 2, g(x) = 6x 10, and h(x) = Find the following (Simplify as far as possible.) (gf)(x) = Submit Question Question 5 Let f(x) = (x - 2) + 2, g(x) = 6x 10, a The economy of country A has two sectors: wheat-growing, and flour-making.In 2015, the wheat growers paid their workers a total of $300 and produced a total of 500 kg of wheat. They sold 100kg directly to consumers, and 400 kg to the flour mills. The selling price for 1 kg of wheat was $1.5.The same year, flour producing firms paid their workers $350. They produced 350kg of flour: 300kg were sold on the local market, and 50kg were shipped abroad as exports. The selling price for 1 kg of flour is $4.Compute the GDP for country A in 2015 = Suppose we are given a simple quadratic function g(w) = wf' w, where WERN. Please estimate the probability of choosing a starting at 0 WO 0 50x1 Suppose the demand for oil is P=197Q-0.20. There aretwo oil producers who form a cartel. Producing oil costs $6 perbarrel. What is the profit of each cartel member? Explain following terms with examples.(a) Lead users(b) Customer Adaptiveness(c) Product Champion(d) Brand Performance(e) Service Recovery(1) Undershot customers(g) Overshot customers(i) What is Relationship Marketing? Explain the drivers of relationship marketingeffectiveness in detail.(ii) Ramsa Corporation is in the business of manufacturing engineering plastics(pellets) for automobile bumpers in Punjab. In order to enter Gujarat, howshould the company go ahead with channel designing? Discuss the role of asymmetric information in explaining financial intermediation. (15 marks) (b) Consider the role of liquidity insurance provision (Diamond and Dybvig) in explaining financial intermediation. (10 marks) Kirtland Corporation uses a periodic inventory system. At the end of the annual accounting period, December 31, 2015, the accounting records for the most popular item in inventory showed the following:TransactionsUnitsUnit Cost Beginning inventory, January 1, 2015380 $3.00 Transactions during 2015: a. Purchase, January 30280 3.20 b. Purchase, May 1440 4.00 c. Sale ($5 each)(140) d. Sale ($5 each)(680)Compute the dollar amount of ending inventory and cost of goods sold at December 31, 2015 under Average cost, First-in, first-out, Last-in, first-out, Specific identification of the inventory costing methods. Specific identification: assuming that the first sale was selected two-fifths from the beginning inventory and three-fifths from the purchase of January 30, 2015. Assume that the second sale was selected from the remainder of the beginning inventory, with the balance from the purchase of May 1, 2015. (Do not round intermediate calculations. Round "Average Cost and Specific Identification" to 2 decimal places.)Need help figuring out the specific identification for ending inventory and cost of goods sold thanks. Solve for: a) y" - 6'' + 5y = 0, y'(0) = 1 and y'(0) = -3 b) F(S) = s^2-4/s^3+6s^2 +9sc) F(s) =s^2-2/ (s+1)(s+3)^2 d) y" + y = sin 2t, y(0) = 2 and y'(0) = 1 Use the integrating factor method to find the solution of the first-order linear differential equation y' + 3y = 3x + 1 which satisfies y(0) = -5.